MHO Renovation Completed

Renovations for Melissa’s Hope Orphanage are completed.  Total cost approximately  $7,500.  We hired over 25 Haitian laborers and purchased over $5,000 worth of Haitian building supplies  including tools.  New paint inside and out.  New storage for the kitchen and bedrooms.  New toilets and sinks in both bathrooms.  New mosquito screens for all of the windows and doors.  7 tons of gravel were delivered to spread around the house.  90′ trench to irrigate the flooding waters from the foothills out of the yard.  New water pump and new generator.  New inverter and new batteries.  Satellite hook-up for wireless internet. Decorations and some furnishings.  We want to thank everyone who helped, especially our hard working friends in Haiti.  After pumping out the septic tanks we discovered that new tanks will be necessary.  This is a big problem.

To see more pictures of the MHO renovations click on Building Projects / 2010 MHO Renovation.